🚧 Scotia Place Construction Update 🚧
Presented by CANA Group of Companies
🏗️ Construction continued to move full speed ahead in June.
✅ Building envelope installation continued to advance on the north side
✅ Roof work progressed on the west side, with installation beginning on the northeast roof truss
✅ Structural steel installation advanced at the northwest entrance and west restaurants
✅ The main arena bowl steel structure is now fully connected
✅ Concrete stadia is now connected around the upper concourse of the main bowl
✅ Significant progress continued on the Esso Community Arena
✅ Work on 14 Avenue S.E. continued, with the road reopened for Stampede
More milestones are ahead as construction continues throughout the summer. ☀️
Scotia Place
Future home to the Calgary Flames, Hitmen, Roughnecks, Wranglers and world-class entertainment. This is just the beginning.
A sneak peek 👀
A part of this year's development camp featured a tour of Scotia Place!
🚧 Scotia Place Construction Update 🚧
Presented by CANA Group of Companies
May brought big progress across the site 🏗️
✅ One-third of the arena roof is now complete
✅ Exterior drywall installation advanced on the west side of the cauldron, while final metal panels were installed on the south side
✅ Concrete stadia installation continued on the east side of the upper bowl
✅ Steel installation progressed on the east bowl and Esso Community Arena entrance
✅ Catwalk installation and interior wall construction continue inside the arena
✅ Progress made on raising 14 Ave SE by 2 metres (6.5 feet)
More exciting progress ahead as Scotia Place continues to transform Calgary’s skyline.
06/15/2026
It's a beauty of a day to get a look at Scotia Place! Calgary Flames Alumni members Robyn Regehr, Lanny McDonald, and Colin Patterson stopped by to check out the construction progress!
🚧 Scotia Place Construction Update 🚧
Presented by
Big milestones taking shape on site last month 🏗️
✅ The main arena roof truss now spans the full width of the seating bowl (341 feet / 104 metres across)
✅ Steel installation continues to climb, reaching the NE entrance and press level while the second roof quadrant takes shape
✅ Precast concrete for the main upper bowl progressed on the north side
✅ Installation of the first exterior cauldron panels is now underway on the south side of the building
More exciting progress ahead as Calgary’s spring weather arrives☀️
🚧 Scotia Place Construction Update 🚧
Presented by
Momentum on site this month 🏗️
✅ Major structural steel progress continues, with two roof trusses now in place in the SW corner and steel climbing on the north side for the upper bowl, food hall and the flagship retail store.
✅ Exterior framing and drywall continue along the South side, moving west above the Indoor Plaza and restaurants
✅ Concrete pours continue, including the loading dock and exterior parkade walls
Plenty more progress ahead, stay tuned 👀
04/15/2026
As Scotia Place continues to rise, we’re excited to give you a closer look at Calgary’s next great gathering space! Our latest renderings showcase spaces that will bring sports, music and community together in one dynamic environment! Check out the Indoor Plaza (a year-round gathering space located at the heart of the building), our flagship retail store, and The Esso Community Arena!
https://www.scotiaplace.com/project-overview/
Major Construction Milestone for Scotia Place 🚧 presented by
The roof is officially going up as the building begins to close in 🏗️ The first of four mega trusses is now in place, marking a huge step forward made possible by months of planning and teamwork.
Designed for flexibility, the roof will support concert rigging and a retractable scoreboard, enhancing the fan experience from every seat.
As the weather warms up, so does the momentum on site ☀️
🚧 Scotia Place Construction Update 🚧
Presented by
February delivered strong progress across the Scotia Place site 🔥
✅ Continued exterior framing and paneling across the site
✅ Expanded steel installation on the west side restaurants and started the indoor plaza entrance
✅Installed precast concrete seating in the upper bowl, with the south side now complete from the first to last row
✅ Installed temporary tower support for the first roof truss
Stay tuned for more updates as Scotia Place continues to rise ✨